Georgia Power has announced more milestones for its Vogtle nuclear power plant expansion project, including the start of hot functional testing for Unit 3 at the facility in Waynesboro, Georgia. The ...
Georgia Power announced that hot functional testing for Unit 4 at the Vogtle nuclear power plant has begun, as the utility moves closer to bringing both reactors of the two-unit expansion at the ...
Southern Co.'s (NYSE:SO) Georgia Power said Monday that Plant Vogtle Unit 4 has started hot functional testing, the last series of critical tests for the new nuclear unit ahead of initial fuel loading ...
CRANBERRY TOWNSHIP, Pa.--(BUSINESS WIRE)--Westinghouse Electric Company today congratulates Southern Nuclear Company, Georgia Power and other project partners for completing hot functional testing at ...
Completion of the testing - which confirms that the reactor is ready for fuel load - is a major step towards commercial operations for the second AP1000 reactor at the site. The unit is projected to ...
One of the key stages of cold and hot functional tests has been completed during a set of commissioning activities, such as blowdown of the fresh steam pipelines in the turbine compartment at Unit 1 ...
Georgia Power announced that hot functional testing began at Vogtle Unit 4, marking one of the final steps for the new nuclear unit ahead of fuel loading. Hot functional testing is conducted without ...